What is a Change Order

Summary: A change order is a formal written agreement that modifies the original construction contract’s scope, schedule, or cost. It documents what changed, why it changed, and the resulting impact on price and timeline. Change orders are the primary mechanism for getting paid for work beyond the original contract scope.

Definition

A change order (CO) is a legally binding modification to a construction contract that alters the original scope of work, contract price, or project schedule. Change orders require agreement from all parties—typically the owner, general contractor, and relevant subcontractors.

Change orders exist because construction projects rarely proceed exactly as originally designed. Design revisions, unforeseen conditions, owner requests, and errors in contract documents all create legitimate reasons to modify the original agreement.

ElementDescription
Scope changeWhat work is being added, deleted, or modified
Cost impactHow the contract price changes (positive or negative)
Schedule impactHow the completion date changes (if at all)
AuthorizationSignatures from parties with contractual authority

Types of Change Orders

By Source

TypeDescriptionExample
Owner-directedChanges requested by the ownerAdding a conference room
Design changesModifications to drawings or specificationsArchitect revises structural details
Field conditionsUnforeseen site conditionsEncountering rock during excavation
Errors and omissionsCorrections to contract documentsMissing electrical panel on drawings
Value engineeringCost-saving alternativesSubstituting equivalent materials
RegulatoryCode or permit requirement changesNew fire safety requirement

By Status

StatusDescription
Potential Change Order (PCO)Identified change not yet priced
Change Order Request (COR)Priced proposal awaiting approval
Approved Change OrderSigned agreement modifying the contract
Rejected Change OrderDenied request (may be disputed)

By Pricing Method

MethodWhen Used
Lump sumWell-defined scope with clear pricing
Time and materials (T&M)Undefined scope, tracked as work proceeds
Unit priceQuantities vary but unit costs are agreed
Cost plusActual costs plus agreed markup

The Change Order Process

Standard Workflow

Trigger Event

Change Identification

Notice to Owner

Pricing/Proposal

Review/Negotiation

Approval

Execution

Billing/Payment

Step-by-Step Process

StepActionsDocumentation
1. TriggerDrawing revision issued, field condition discovered, owner request receivedRevised drawings, RFI, meeting minutes
2. IdentificationIdentify scope change and affected workChange comparison, scope analysis
3. NoticeNotify owner within contract-required timeframeWritten notice per contract requirements
4. PricingEstimate cost and schedule impactDetailed breakdown, subcontractor quotes
5. ReviewOwner/architect review and negotiateCorrespondence, clarifications
6. ApprovalAll parties sign change orderExecuted change order document
7. ExecutionPerform the changed workDaily logs, progress photos
8. BillingInclude in pay applicationSchedule of values update

Critical Timelines

Most contracts specify notice requirements for change orders:

Contract TypeTypical Notice Requirement
AIA contractsWithin 21 days of event
ConsensusDocsWithin 14 days of event
Federal (FAR)Within 20 days of event
Custom contractsVaries (read your contract)

Missing notice deadlines can waive the right to additional compensation, even for legitimate scope changes.

What Triggers Change Orders

Drawing Changes

Drawing revisions are a primary source of change orders in construction. Every time the design team issues revised drawings, contractors must review for scope changes.

Drawing ChangePotential Change Order Impact
Added elementsAdditional work and materials
Deleted elementsCredit for work no longer required
Dimension changesMore or less material/labor
Specification updatesDifferent materials, methods, or equipment
Detail revisionsModified installation requirements
Layout modificationsRework if work already in place

The Documentation Challenge

The challenge is identifying what actually changed in revised drawings. With drawing sets of 100-1,000+ pages, manually finding changes is:

  • Time-consuming (hours per revision)
  • Error-prone (missed changes = missed change orders)
  • Inconsistent (different reviewers find different changes)

This is why automated drawing comparison is critical for change order management—it ensures no scope-impacting change goes undetected.

Other Common Triggers

TriggerExample
RFI responsesArchitect clarification adds scope
Substitution requestsApproved alternative affects installation
Coordination conflictsTrades require redesign to fit
Owner decisionsSelection of higher-grade finishes
Permit conditionsAdditional fire stopping required
Concealed conditionsExisting conditions differ from documents

Documentation Requirements

Essential Change Order Documentation

DocumentPurpose
Change order formFormal document modifying contract
Detailed scope descriptionExactly what work is added/deleted/modified
Cost breakdownLabor, material, equipment, subcontractor costs
Supporting calculationsQuantities, production rates, hours
Subcontractor quotesPricing from affected subs
Schedule analysisTime impact justification
Drawing referencesSpecific sheets and revisions affected
CorrespondenceEmails, RFIs, meeting notes establishing cause

Cost Breakdown Structure

A defensible change order includes detailed cost buildup:

CategoryComponents
Direct laborHours by trade, wage rates, burden
MaterialsQuantities, unit costs, delivery
EquipmentRental rates, ownership costs
SubcontractorsSub quotes with their breakdowns
MarkupOverhead and profit per contract terms
Bond/insuranceIf contract requires adjustment

Schedule Impact Documentation

When changes affect the schedule:

ElementDocumentation
Impact analysisHow the change affects critical path
Time extension requestDays requested with justification
Updated scheduleRevised CPM showing impact
Acceleration costsIf schedule compression is required

Why Change Order Tracking Matters

Financial Impact

RiskConsequence of Poor Tracking
Unbilled workPerforming scope changes without compensation
Margin erosionProfit consumed by untracked extra work
Cash flowDelayed billing on changed work
DisputesContested claims without documentation

Studies show that poor change management contributes to cost overruns of 10-15% on typical projects, with severe cases exceeding 30%.

RiskConsequence
Waived claimsMissing notice deadlines forfeits recovery rights
Disputed scope”That was always in the drawings” without proof
Audit exposureInability to justify costs to owner/auditor
Litigation disadvantageWeak documentation in legal proceedings

Relationship Impact

RiskConsequence
Owner distrustPerception of inflated or unjustified claims
Subcontractor disputesBackcharges for untracked scope changes
Team frictionFinger-pointing over responsibility

How Drawing Comparison Supports Change Orders

Automated drawing comparison directly supports change order management:

Identification

Manual ProcessWith Drawing Comparison
Hours reviewing drawingsMinutes for entire set
Missed changes commonComprehensive detection
Subjective interpretationObjective documentation
Reviewer fatigueConsistent analysis

Documentation

Drawing comparison creates evidence for change order justification:

  • Visual overlays showing exactly what changed
  • Change reports listing all modifications by sheet
  • Timestamps proving when changes were identified
  • Objective record independent of interpretation

Timeliness

Faster change identification means:

  • Meeting contractual notice deadlines
  • Pricing changes before work begins
  • Avoiding “out of sequence” change orders
  • Proactive rather than reactive change management

Best Practices

PracticeImplementation
Read your contractKnow notice requirements, markup allowances, dispute procedures
Document everythingDaily logs, photos, correspondence for every potential change
Compare every revisionUse automated tools to ensure nothing is missed
Submit timely noticeNever miss contractual notice deadlines
Price accuratelyDetailed breakdowns prevent negotiation erosion
Track pending changesMaintain log of all potential and submitted change orders
Communicate proactivelyEarly owner notification reduces disputes
Preserve recordsMaintain documentation for warranty period + statute of limitations

FAQ

What’s the difference between a change order and a change directive?

A change order is a mutually agreed modification with agreed pricing. A change directive (or construction change directive) is an owner instruction to proceed with changed work while pricing is still being negotiated. Directives are used when work cannot wait for pricing agreement.

Can I be forced to do change order work without agreement on price?

Most contracts require contractors to proceed with owner-directed changes even without price agreement, with the price to be determined later. Refusing to proceed may be considered breach of contract. The remedy is to dispute the pricing, not refuse the work.

What if the owner disputes that a change order is warranted?

Document your position thoroughly, including the contract language, original drawings, and changed drawings. If agreement cannot be reached, most contracts specify dispute resolution procedures (negotiation, mediation, arbitration, or litigation).

How do I track changes across multiple drawing revisions?

Maintain a revision log tracking all drawing issues. Compare each revision to the previous version (not just to original bid documents) to catch cumulative changes. Automated comparison tools make this practical for large drawing sets.

What markup is allowed on change orders?

Markup (overhead and profit) is typically specified in the contract. Common ranges are 10-15% for general contractor work and 5-10% for subcontractor work passed through. Some contracts cap total markup on multi-tier changes.

Key Takeaways

  • Change orders formally modify contract scope, cost, or schedule
  • Required for getting paid for work beyond original contract scope
  • Types include owner-directed, design changes, field conditions, and errors/omissions
  • Process: trigger, notice, pricing, review, approval, execution, billing
  • Drawing changes are a major source of change orders in construction
  • Meeting notice deadlines is critical—late notice may waive claims
  • Documentation requirements include detailed scope, cost breakdown, and schedule impact
  • Automated drawing comparison ensures no scope change goes undetected
  • Poor change order management contributes to cost overruns of 10-15%+

Last updated: 2026-02-04